Drawings for all items like boiler, economizer, valve, pipings etc under IBR shall be submitted for approval from department and approved shall be obtained before commencement of manufacturing/fabrication activity.
- Submission of Application along with
- Drawings
- Design calculations
- Requisite Receipted Challan for prescribed fees
- Scrutiny by Technical assistant / Technical officer
- Review by Jt. Director (only carbon steel piping drawing upto 6” dia x100 mtr.length)
- Review by Director.
- Delivery / Dispatch of approved drawings.
Every such application shall be accompanied by relevant physical documents as listed below.