Inspection During Manufacturing of Saw Pipes

  • Submission of application for inspection of raw material & challan.
  • Inspection by officer
  • Director’s review and visit for selection of sample for testing.
  • Physical & chemical testing of sample.
  • After review by Director hydraulic test.
  • Submission and approval of maker’s certificate.

Every such application shall be accompanied by relevant physical documents as listed below.

Sr. No. Title Download
1 Required filling Form PDF file that opens in new window. To know how to open PDF file refer Help section located at bottom of the site. (29 KB)

Mandatory - Items

  • Application for inspection of raw material, Date of visit required.
  • Receipted Challan for prescribed fees.